Buying an off-plan apartment in Fortaleza, Brazil: how payments work, from deposit to keys

Deposit, installments, INCC index, financing at handover and the 2% ITBI tax in Fortaleza. A step by step guide to buying off-plan in Brazil.

By Erika SantosReal estate broker in Fortaleza, with more than 10 years in the market

Published on 6 min read

Buying off-plan in Fortaleza: tall buildings of the city under a blue sky
Photo: Joelkaula (CC BY-SA 4.0), Wikimedia Commons

How paying for an off-plan apartment works

Buying an off-plan apartment in Fortaleza means buying before or during construction, directly from the developer. The price is split into a payment schedule defined by each project. The stages usually look like this:

StageWhenWhat it is
DepositAt signingThe first part of the price, paid right at the start
Monthly installmentsDuring constructionSmaller amounts, month by month, until handover
Interim paymentsOn agreed datesLarger yearly or half-yearly payments, present in some schedules
KeysAt handoverThe remaining balance, paid in cash or financed by a bank

The split between stages changes from one project to another, and sometimes within the same project depending on the sales stage. That is why, before comparing two apartments, I always ask for the current price list of each one. Comparing prices without comparing schedules means comparing different things.

What INCC is and why the balance changes during construction

During construction, installments and the balance are usually adjusted by the INCC, the National Construction Cost Index calculated by FGV. It follows the cost of materials and labor. In practice, the balance you will pay at handover is not the same as on the day you bought: it rises with the index.

After handover, if part of the balance is still paid directly to the developer, the contract usually switches to another index and may add interest. Read that clause carefully, because it defines how much you will pay after getting the keys.

Financing at handover

At handover, the balance is settled. If you will finance it, the bank approves the loan close to the end of construction, reviewing your income and appraising the apartment. If the bank values the apartment below expectations, or your income does not support the installment, the difference comes out of your pocket.

That is why I recommend simulating the financing at the time of purchase, with the estimated and adjusted balance, not only in the year of handover.

ITBI and registration in Fortaleza: the final costs

To put the apartment in your name, two costs apply: ITBI, the municipal property transfer tax, and registration at the real estate registry. In Fortaleza, ITBI rates are set in article 306 of the Municipal Tax Code (Complementary Law 159/2013, as amended by Complementary Law 318/2021):

SituationRate
Portion financed through the SFH housing finance system, up to R$ 200,0000.5%
Non-financed portion and other purchases4%
Non-financed portion and other purchases, with the tax paid before the deed or contract is signed2%

Example: an apartment of R$ 800,000, with R$ 200,000 financed through the SFH and the tax paid before signing. That is 0.5% of R$ 200,000 (R$ 1,000) plus 2% of R$ 600,000 (R$ 12,000), a total of R$ 13,000 in ITBI.

The tax base is the market value of the property, according to article 303 of the same code. Registration follows the registry fee table, which varies with the value. When there is bank financing, the bank contract is used for the registration.

What Brazilian law guarantees off-plan buyers

  • Registered development. The developer can only sell units after registering the development at the real estate registry (Law 4,591/1964, article 32). Ask for the registration number.
  • Patrimônio de afetação. When the project adopts this regime (Law 10,931/2004), the money and the land of that development are kept separate from the company's other debts.
  • Grace period. Delivery may be up to 180 calendar days late without penalty, if the contract states it clearly (Law 13,786/2018).
  • Right to withdraw. A contract signed at a sales stand or outside the developer's office can be undone within 7 days, with a full refund, including the brokerage fee.
  • Cancellation. If you cancel after that, the developer may keep the brokerage fee and a penalty of up to 25% of what you paid, or up to 50% when the project has patrimônio de afetação.

Checklist before signing

  1. Current price list and payment schedule in writing.
  2. Registration number of the development and whether it has patrimônio de afetação.
  3. Expected delivery date and grace period clause.
  4. Adjustment index during and after construction.
  5. Financing simulation with the adjusted balance, or a cash plan for the balance.
  6. Estimate of ITBI, registration and condo fees.
  7. Specification sheet, which lists what comes installed in the apartment.

The developments I follow in Fortaleza are in the listings on the site, grouped by stage. If you are looking at a specific area, the guide living in Guararapes puts the three developments of that neighborhood side by side.

Properties mentioned in this article

Frequently asked questions

How much is ITBI in Fortaleza?

The general rate is 4%, reduced to 2% when the tax is paid before the deed or contract is signed. When buying through the SFH housing system, the financed portion up to R$ 200,000 pays 0.5%. This is set in article 306 of the Fortaleza Tax Code.

What is INCC when buying off-plan?

It is the National Construction Cost Index, calculated by FGV. During construction, it usually adjusts the installments and the balance you will pay at handover.

Can I cancel an off-plan purchase?

If the contract was signed at a sales stand or outside the developer's office, you have 7 days to change your mind and get everything back. After that, the developer may keep the brokerage fee and a penalty of up to 25% of what you paid, or up to 50% when the project has patrimônio de afetação.

Can foreigners buy an apartment in Fortaleza?

Foreigners can buy urban property in Brazil. You will need a CPF, the Brazilian taxpayer number, which the Receita Federal issues to foreign citizens, including through Brazilian consulates. I also recommend a local lawyer to review the contract.

What if construction is delayed?

The contract may allow up to 180 days of tolerance without penalty, if stated clearly. After that period, and if you did not cause the delay, you can cancel the contract and get back everything you paid plus the agreed penalty.

Sources